Project Schedule (Phase 1)
Spatial Programming June - July 2006
Preliminary Site Study June - July 2006
City Preliminary Development Plan, Street Vacation, and Plat Submittal
· Pre-applicants Meeting Aug 16, 2006 · Application Due Aug 30, 2006 · Plan Commission Date Oct. 02, 2006 · City Council Oct. 17, 2006
City Final Development Plan Submittal
· Submittal Nov. 01, 2006 · Plan Commission Date Dec. 04, 2006 · City Council Dec. 19, 2006
Building Permit · Applicants Dec 14, 2006 · Issues Feb. 01, 2006
Schematic Design Jul 10 – Aug 25, 2006
Design Development Aug 25 – Oct 25, 2006
Construction Documents Oct 27 – Dec 14, 2006
QC Review Dec. 14 - 28, 2006
Construction Phase I March, 2007 – Fall, 2008
|
|