Project Schedule (Phase 1)

 

Spatial Programming                 June - July 2006

 

Preliminary Site Study               June - July 2006

 

City Preliminary Development Plan, Street Vacation, and Plat Submittal

 

· Pre-applicants Meeting      Aug 16, 2006

· Application Due                  Aug 30, 2006

· Plan Commission Date      Oct. 02, 2006

· City Council                       Oct. 17, 2006

 

City Final Development Plan Submittal

 

· Submittal                            Nov. 01, 2006

· Plan Commission Date      Dec. 04, 2006

· City Council                       Dec. 19, 2006

 

Building Permit

· Applicants                         Dec 14, 2006

· Issues                                Feb. 01, 2006

 

Schematic Design                      Jul 10 – Aug 25, 2006

 

Design Development                 Aug 25 – Oct 25, 2006

 

Construction Documents          Oct 27 – Dec 14, 2006

 

QC Review                                  Dec. 14 - 28, 2006

 

Construction Phase I                 March, 2007 – Fall, 2008

 